Owner-builder in Victoria: consent, the building permit and your duties

Permits and approvals

Published · Updated · 9 min read

In short: To be an owner-builder in Victoria, you need a certificate of consent from the Building and Plumbing Commission (BPC) for domestic building work costing more than $20,000. You must own the land, live or intend to live in the home and pass an online assessment. You still need a building permit and mandatory inspections, and a defects report and insurance if you sell within 6 years and 6 months.

Key takeaways

  • Owner-building domestic work that costs more than $20,000, including labour and materials, needs a certificate of consent from the Building and Plumbing Commission.
  • A certificate of consent is not a building permit. You still need a permit, drawings showing structural members, and inspections at mandatory stages.
  • Some small jobs need no building permit under Schedule 3 of the Building Regulations 2018, such as a non-masonry shed of 10 m² or less.
  • Owner-builders can't carry out demolition or subfloor work, such as restumping or reblocking. Registered building practitioners must do that work.
  • Selling within 6 years and 6 months of completion requires a defects report, insurance with a notice of cover, and statutory warranties in the contract.
A new single-storey timber-framed house under construction on a suburban block, with pine wall frames and roof trusses standing on a concrete slab, stacks of timber on the ground and an overcast sky

Owner-building in Melbourne? Get structural drawings for your building permit or call 03 7048 4006.

You need a certificate of consent before carrying out domestic building work as an owner-builder in Victoria when the work costs more than $20,000. The rule is section 25B of the Building Act 1993. The certificate comes from the Building and Plumbing Commission (BPC), the trading name of the Victorian Building Authority (VBA).

The BPC says the cost of the work includes labour and materials, estimated as if a registered builder did it. Under its certificate of consent rules, you don't need one if the work isn't domestic building work, if a registered building practitioner is nominated on the building permit as responsible for it, or if you're working under an emergency order, building notice or building order.

Some guidance, including the Consumer Affairs Victoria owner builders page, still shows $16,000 rather than $20,000.

Who can be an owner-builder in Victoria?

You can be an owner-builder in Victoria if you own the land, the work is for a single home you live in or intend to live in, and you meet the knowledge and five-year rules in section 25E of the Act, set out on the BPC's eligibility page.

Requirement What it means
Ownership You own the land, or are a director or beneficiary of the company or trust that owns it, with written authority
One home A single dwelling, or work ancillary to it such as a garage, pool, fence, pergola or retaining wall
Living there You live there or intend to, unless it is a small second dwelling
Knowledge You pass the BPC's eLearning assessment and complete construction induction training (a white card)
Five-year rule No owner-builder building permit for a different property, issued to you or a co-owner, in the previous 5 years, unless the BPC exempts you for special circumstances
Past sales The BPC must refuse you if you ever contracted to sell an owner-built home without the required insurance

You also can't be in the business of building.

What work can't an owner-builder do in Victoria?

Owner-builders in Victoria can't carry out demolition or subfloor work, such as restumping or reblocking, and can't relocate a home; the BPC says registered building practitioners must do it. Consumer Affairs Victoria's owner builders checklist also says to use registered builders to reblock, restump, demolish or remove a home, regardless of value.

When you hire others, the BPC's during the build page says work over $10,000 needs a major domestic building contract with a registered builder, unless a single-trade exemption applies. Section 25B(1A) of the Act makes signing that contract with an unregistered builder an offence, and section 25B(1B) excuses you if you took reasonable steps to check the builder's registration.

What are an owner-builder's duties in Victoria?

An owner-builder in Victoria takes on the responsibilities, risks and liabilities of a professional builder, according to the BPC's owner builder information and study guide. The guide, the BPC and Schedule 2 of the Building Regulations 2018 list duties including:

  • getting a building permit, paying the levy, and telling the BPC if the estimated cost has risen by the end of the project;
  • supervising all the work and making sure it complies with the Act and the Regulations;
  • site safety under the Occupational Health and Safety Act 2004, including inducting each worker before they start;
  • arranging any required protection work for neighbouring property;
  • a site sign with your contact and permit details, and the permit and approved plans kept on site;
  • fixing defects or non-compliances for a later owner for 10 years from completion.

What requires a building permit in Victoria?

Building work in Victoria needs a building permit unless the Building Regulations 2018 exempt it. Section 16 of the Building Act 1993 says a person must not carry out building work unless a building permit for the work has been issued and is in force, and regulation 23 points to the exemptions in Schedule 3. The BPC's practice note BP 01 explains that constructing a building includes building, re-building, repairing, altering, extending and relocating it.

These are some of the Schedule 3 exemptions most owner-builders ask about. Each one has conditions, so read the full item before relying on it.

Work Exempt from a building permit when Needs a permit when
Shed, garage or carport (freestanding Class 10a) Floor area 10 m² or less, no more than 3 m high (2.4 m within 1 m of a boundary), not masonry, and sited as the item requires It is larger, taller, masonry or sited forward of the house
Pergola (open and unroofed) No more than 3.6 m high, floor area 20 m² or less, and no more than 2.5 m forward of the front wall of a house It has a roof, or is larger, taller or further forward
Fence (not a pool barrier) No more than 2 m high, with lower limits within 3 m of a street (1.5 m, or 1.2 m if masonry or concrete) and 1 m near a corner It is higher than these limits
Retaining wall Less than 1 m high and not linked to other building work or to protecting a neighbour's property It is 1 m or higher, or part of other building work
Deck or verandah Never exempt when attached to a house or pool, according to BP 01 Attached decks of any size, and detached decks serving a building
Repairs and alterations They don't affect structural soundness, footings, floor area, height or any load-bearing element They involve underpinning, new footings or removing a supporting wall

The BPC notes that an exempt structure must still be designed to resist the loads on it, and that a planning permit may still be needed. If an alteration removes or changes a load-bearing element, it needs a permit, and the permit drawings must show the new structural members, as with load-bearing wall removal.

What happens if you build without a building permit in Victoria?

Building without a required permit is an offence under section 16 of the Building Act 1993, with a maximum penalty of 500 penalty units for a person and 2,500 penalty units for a company. A penalty unit is worth $209.10 from 1 July 2026 to 30 June 2027, according to the Department of Treasury and Finance, so the maximum for a person is $104,550. Section 16(3) also makes the owner of the land responsible for making sure a permit is in force, unless they engaged a building practitioner, endorsed building engineer or architect to carry out the work.

A municipal or private building surveyor can also serve a building notice on the owner when work was done without a required permit (section 106). After considering the owner's response, the surveyor can make a building order directing the owner to carry out building work (section 111).

Do owner-builders still need a building permit and structural drawings?

Yes: a certificate of consent only lets you act as the builder, so you still need a building permit, and the permit application needs drawings that show the structural members. Section 16 of the Act makes it an offence to carry out building work without a permit in force.

You can appoint your council's municipal building surveyor or a private one. They must not issue a permit if a required planning permit hasn't been obtained or the work won't comply.

Regulation 25 of the Building Regulations 2018 says an application to construct or alter a building must include drawings showing plans, elevations, sections and the sizes and locations of structural members; specifications; an allotment plan; and any computations or reports needed to show the work will comply. Section 238 of the Act lets the building surveyor rely on a certificate from an endorsed building engineer or a registered building practitioner that proposed building work complies.

Which inspections does an owner-built home need?

An owner-built home needs an inspection at each mandatory notification stage the building surveyor lists on the permit, chosen from regulation 167 of the Building Regulations 2018. The study guide says the owner-builder must notify the building surveyor at each stage, and failing to do so attracts 120 penalty units.

Stage When to notify the building surveyor Notes
Footings Before placing a footing BPC practice note MI 01: a pre-slab inspection also checks siting
Reinforced concrete Before pouring an in situ reinforced concrete member specified in the permit MI 01 examples: concrete stairs, bond beams, reinforced retaining walls and columns
Frame On completion of the framework The study guide suggests asking about voluntary pre-plaster or waterproofing inspections
Final On completion of all building work Then an occupancy permit (new home) or certificate of final inspection (extension or alteration)

The building surveyor may leave out a stage that isn't relevant (regulation 170). MI 01 says an engineer you engage doesn't replace a mandatory inspection; only the building surveyor can cause one.

What do you need to sell an owner-built home in Victoria?

If you sell an owner-built home within 6 years and 6 months of the completion date, section 137B of the Act requires a defects report, compliance with the statutory insurance scheme, a notice of cover for the buyer and set warranties in the contract. The completion date is the date of the occupancy permit or, if none is issued, the certificate of final inspection.

What you need Detail
Defects report From a prescribed building practitioner, such as a registered architect, registered building surveyor or building inspector, or endorsed building engineer; no more than 6 months old at the contract; copy to the buyer
Insurance Bought before the contract of sale, where the project was valued over $20,000 (BPC). The BPC's page also refers to Home Warranty, which replaced domestic building insurance for new eligible work from 1 July 2026
Notice of cover Given to the buyer; the BPC says to include it, with the defects report, in the section 32 statement
Warranties Section 137C: proper and workmanlike work, good and suitable materials (new unless the contract says otherwise), and compliance with all laws

The BPC says defects listed in the report are excluded from the cover, and later owners can also rely on the warranties (s137C). Breaching section 137B attracts 100 penalty units, and the contract is voidable at the buyer's option before completion. Some BPC wording gives six years instead, so check your dates with the BPC before listing.

What else applies to owner-builders in Melbourne?

Melbourne owner-builders follow the same Victorian rules, plus their council's planning scheme. The BPC's study guide also flags these points:

  • Planning permit. Many new buildings, additions and renovations need a planning permit from your local council, which decides whether you need one.
  • Bushfire prone areas. Check the state's bushfire prone area maps early.
  • Asbestos. A home built before 1990 is likely to contain asbestos, so find out before you start.

When to call a structural engineer

Call a structural engineer before you apply for the building permit if your project includes new footings or a slab, beams, an upper floor or a retaining wall, so the member sizes and computations regulation 25 asks for are ready. Our residential structural design service prepares permit drawings and calculations, including for owner-builders. Also call if:

To get a quote, send your drawings, photos of the existing house, your suburb and any request from your building surveyor.

Frequently asked questions

What size shed doesn't need a building permit in Victoria?

A freestanding shed, garage or carport with a floor area of 10 m² or less is exempt under item 1 of Schedule 3 of the Building Regulations 2018, if it is no more than 3 m high (2.4 m within 1 m of a boundary), isn't masonry and meets the siting conditions. The BPC notes that a planning permit may still be needed.

How much does a building permit cost in Victoria?

There is no set price. The cost depends on the fee of the building surveyor you choose (municipal or private), any council report and consent fees, and the building permit levy under section 205G of the Building Act 1993. That levy is two charges of 0.064 cents per dollar of the cost of the work, and it isn't payable when the work costs $10,000 or less.

How long does it take to get a building permit in Victoria?

For a house or outbuilding (Class 1 or 10), regulation 35 of the Building Regulations 2018 gives the building surveyor 10 business days to decide, counted from when any required reports and consents (for example from the council) are in or fall due. A reporting authority has 10 business days for most reports, or 15 for siting matters. Once issued, work must start within 12 months and a house must be finished within 24 months, unless extended.

Can an owner-builder do their own electrical or plumbing work in Victoria?

Only with the right licence or registration. The BPC's study guide says plumbing and gasfitting must be done by plumbers licensed or registered by the BPC, and electrical wiring only by electricians licensed by Energy Safe Victoria. Consumer Affairs Victoria says to get a plumber's compliance certificate for plumbing work costing $750 or more, and a Certificate of Electrical Safety for all electrical installation work.

How much does a certificate of consent cost, and how long does it last?

Regulation 18 of the Building Regulations 2018 sets the non-refundable application fee at 14.42 fee units, and the BPC says processing takes about 45 business days when all the required information is provided. The certificate lasts 12 months from issue or, if a building permit is issued in that time, until the permit lapses.

A builder has asked me to sign the building permit as the owner-builder. Should I?

Be wary. The BPC says you are not an owner-builder if one builder or tradesperson does all the work, and the person asking may be unregistered or avoiding their legal responsibilities. If you agree, you are responsible for the work to any later owner, and Consumer Affairs Victoria suggests getting advice first.

Can buyers find out that a home was owner-built?

Yes. The BPC keeps a public register of certificates of consent issued from 1 September 2016, showing the property address and details of the building work. Its study guide says entries stay on the register for 10 years, so buyers can see that a home was owner-built and ask whether the vendor has met the selling obligations.

Do I need insurance while I'm building?

Schedule 2 of the Building Regulations 2018 lists obtaining insurance for loss, damage or injury to you or others during the work among an owner-builder's duties. The BPC's study guide adds that your insurance must cover damage from any protection work during construction and for 12 months after completion, and that you may need to join the WorkCover scheme if your site is a workplace.

Sources

  1. Building and Plumbing Commission: Certificate of Consent
  2. Building and Plumbing Commission: Owner-builder eligibility
  3. Building and Plumbing Commission: What is an owner-builder?
  4. Building and Plumbing Commission: During the build
  5. Building and Plumbing Commission: Selling an owner-built home
  6. Building and Plumbing Commission: Owner builder information and study guide (version 6.0)
  7. Building and Plumbing Commission: e-Learning portal and study guide
  8. Building and Plumbing Commission: Apply to be an owner-builder
  9. Building and Plumbing Commission: Construction induction and white cards
  10. Building and Plumbing Commission: Home Warranty
  11. Building and Plumbing Commission: Practice note MI 01, Mandatory notifications and inspections of building work
  12. Victorian Legislation: Building Act 1993 (sections 16, 19, 25B, 25E to 25G, 106, 111, 137B, 137C, 205G and 238)
  13. Victorian Legislation: Building Regulations 2018 (regulations 18, 23, 25, 34, 35, 53 to 55, 167 to 171 and Schedules 2 and 3)
  14. Building and Plumbing Commission: Practice note BP 01, When is a building permit required
  15. Building and Plumbing Commission: Appointing a building surveyor
  16. Department of Treasury and Finance (Victoria): Indexation of fees and penalties
  17. Consumer Affairs Victoria: Owner builders
  18. Consumer Affairs Victoria: Owner builders checklist