When do you need an asset protection permit in Melbourne?

Permits and approvals

Updated · 6 min read

In short: An asset protection permit is a council permit that protects footpaths, kerbs, nature strips, vehicle crossings and drains from damage during building work. Boroondara, Darebin, Glen Eira, Merri-bek, Monash and Whitehorse councils require one before works start, but each sets its own triggers and fees. Darebin requires one for any project needing a building permit. Where held, bonds are refunded after a final inspection, once any damage is repaired.

Key takeaways

  • Councils issue asset protection permits; a building surveyor issues the building permit. Darebin says works can start only when both are in place.
  • Darebin requires one for any project needing a building permit; Merri-bek for building works over $5,000, and underpinning or re-blocking at any value.
  • Bonds vary: in October 2026, Glen Eira listed $2,000 (single frontage) or $5,000 (corner lot); Boroondara's minimum was $3,000 for minor works.
  • Record existing damage first: Whitehorse requires a pre-commencement report with photos, and Merri-bek assumes assets were in good condition if you supply none.
  • A final inspection decides the bond refund. Boroondara pays refunds within 8 weeks, and Whitehorse says they can take up to 8 weeks.
Low view along a concrete kerb at the edge of a dark asphalt road, with a grass nature strip and concrete footpath behind it, a long grey corrugated site fence and a blurred new timber house frame beyond, under an overcast sky

Planning an extension, new home, restump or demolition in Melbourne? Get a quote or call 03 7048 4006, and send your plans and the name of your council.

What is an asset protection permit?

An asset protection permit is a council permit that protects public assets next to a building site, such as footpaths, kerbs and drains, from damage during building or demolition work. The City of Boroondara lists the assets its permit covers as footpaths, nature strips, vehicle crossings (the strip of driveway that crosses the footpath and nature strip), kerbs, channels, drains, roads and laneways, and parks, gardens and reserves. Glen Eira also names trees and signs.

The permit protects owners too. The Australian Business Licence and Information Service (ABLIS) listing for Monash says it protects owners and builders against paying for damage that was already there. Merri-bek warns that owners are responsible for damage to its assets "even if the damage is caused by your builder, contractor or sub-contractor".

When do you need an asset protection permit in Melbourne?

You need an asset protection permit before building or demolition works start, but each Melbourne council sets its own trigger. Whitehorse notes that its local law "may be different from the local laws in other municipalities" (Whitehorse Community Local Law), so check the council for your property.

Council When the council says you need one Fee and bond listed by the council
Boroondara Building works or demolition that may affect council assets Application fee $354 and bond of at least $3,000 for minor works such as re-stumping or fencing; $528 and at least $5,000 for medium works such as extensions or pools
Darebin Any project that needs a building permit, including demolition Fee and bond vary with the scope and budget of the works
Glen Eira Building or demolition works, except minor works under $5,000, with no masonry or demolition, that don't need a building permit $400 permit fee; bond of $2,000 for a single-frontage residential lot or $5,000 for a corner lot
Merri-bek (named Moreland until 2022) Building works over $5,000, plus separate permits for demolition, underpinning, re-blocking and removal of buildings and structures at any value 2026/27 permit fees from $208.50 to $4,175, by type of work; the page lists no bond
Monash Listed works including demolition, construction, renovation, restumping, excavation, landscaping and concreting; verandas, pergolas and decking only over $30,000 Fees plus a refundable security deposit, set in Council's fee schedule
Whitehorse When a building permit has been issued or building or demolition works are proposed An application fee and a security bond; additional bonds may apply for corner blocks, double frontages or multi-unit developments

Fees and bonds are as shown on each council's page in October 2026; check before you apply.

Whitehorse says owners or contractors must get the permit at least seven days before building work starts. Boroondara and Merri-bek say works can't start until you have received the permit, and Merri-bek processes applications within 5 full business days.

How do asset protection bonds and inspections work?

An asset protection bond is held while the works happen and refunded once a final council inspection finds the footpaths, kerbs, vehicle crossings and drains undamaged or properly repaired.

  1. Record the condition before works. Darebin's first inspection records the condition of council assets before work starts and doesn't need you or your builder on site. Whitehorse's pre-inspection identifies existing damage, and you don't need to book it.
  2. Add your own evidence. Whitehorse requires a pre-commencement report with photos of nearby assets such as the footpath, kerb, road, signs and trees. Monash recommends your own photographic evidence. Merri-bek recommends a dilapidation report or photos; without them, it assumes all assets were in good condition. Glen Eira says telling it about existing damage before works protects you from paying for that damage.
  3. Protect the assets during works. Merri-bek may inspect the site during construction to make sure its assets are undamaged.
  4. Restore the site and ask for the final inspection. Boroondara expects rubbish and building materials removed, damage repaired, and damaged nature strips levelled and seeded. Monash asks to be notified within 28 days of the works being completed. If a Whitehorse final inspection fails, the damaged area must be made safe straight away, and repairs should be completed within 45 days.
  5. Get the bond back. Boroondara refunds the bond in full within 8 weeks if the site meets the permit conditions. Monash refunds its security deposit automatically after the final inspection if there is no damage.

How does an asset protection permit fit with the building permit?

An asset protection permit sits alongside the building permit rather than replacing it: the council issues the asset protection permit, and a building surveyor issues the building permit. The Building and Plumbing Commission (BPC), the trading name of the Victorian Building Authority (VBA), says any project that requires a building permit needs a building surveyor, municipal (council) or private. The surveyor issues the permit that allows work to start, carries out inspections, and issues an occupancy permit or certificate of final inspection at the end.

Stage Building permit Asset protection permit
How it starts The owner (or their agent) appoints a private building surveyor, or applies to the council's municipal surveyor; a private surveyor must notify the council within seven days of being appointed In Darebin, the surveyor's notice of engagement (which Darebin calls a "Section 80") starts the asset protection process
Before work starts The building surveyor issues the building permit Councils such as Darebin and Whitehorse inspect their assets first; Darebin says works can start only when both permits are in place
When work ends Occupancy permit or certificate of final inspection Darebin's final inspection follows either document; Whitehorse's needs the occupancy permit issued

Darebin's invoice for the fee and bond must be paid 7 days before any works start. Building it yourself? Our owner-builder guide explains why owner-builders still need a building permit and a building surveyor.

Asset protection rules in Victoria: local laws and penalties

In Victoria, asset protection permits are council rules, so the local law and the penalty depend on the council.

  • Boroondara: Protection of Council Assets and Control of Building Sites Local Law 2021.
  • Glen Eira: Community Local Law 2019. Starting building works without a permit is an offence under clause 15(1), and penalties of up to $2,000 may apply. Damaging council assets during works may also bring a penalty of up to $2,000, plus the full cost of repair or replacement.
  • Merri-bek: General Local Law 2018. Council issues asset protection and road management fines for breaching a permit requirement, not getting a required permit, excavating outside a property boundary without approval, and failing to notify it that permitted works are finished.
  • Monash: Community Safety and Amenity Local Law 2024 (named in the ABLIS listing). Monash says non-compliance with permit conditions may result in an infringement.
  • Whitehorse: Community Local Law 2024, which covers asset protection permits under preventing damage to council property.
  • Darebin: its page doesn't name a local law, but says a fine may be issued if works start without an asset protection permit.

When to call a structural engineer

Call a structural engineer when works that need an asset protection permit also need structural design, or will dig or drain near council land.

  • Extensions, second storeys and new homes. The BPC says the building surveyor checks the permit application against the Building Act 1993, Building Regulations 2018 and National Construction Code. Our residential structural design page covers the structural drawings and calculations for it.
  • Restumping, re-blocking and underpinning. Some councils require a permit for these works alone, as the table shows. Before choosing a fix, a structural inspection looks at the cracking, footing movement or sloping floors that prompted it.
  • Excavation, retaining walls and basements near the front boundary. Monash lists excavation among the works that need a permit. Our retaining wall design page explains when a wall close to a boundary, or one carrying a driveway, generally needs an engineer.
  • A new stormwater connection. Boroondara needs a separate Road Opening Permit to install or repair a stormwater connection, and Glen Eira an Asset Consent Permit to connect to its drainage network. Our civil and stormwater engineering page explains the legal point of discharge, where your stormwater must meet the public system.

Frequently asked questions

Who applies for the asset protection permit, the owner or the builder?

It depends on the council. Monash says getting the permit is the property owner's responsibility, Whitehorse says property owners or contractors must obtain it, and Glen Eira puts the duty on the person in charge of the building site. Whoever pays the bond should expect to claim it back: Boroondara and Whitehorse only take refund applications from the person or company who paid it.

Do I need a separate permit to change a driveway crossover?

In some councils, yes. Boroondara needs a Vehicle Crossing Permit for any change to a vehicle crossing, minor or major, temporary or permanent. Merri-bek lists a 2026/27 vehicle crossing permit fee of $241 among its extra fees, and Monash won't do its final asset inspection until 1 month after a new crossing is poured.

Can one asset protection permit cover the demolition and the new build?

Not in Merri-bek, which needs separate permits for demolition and construction. In Monash, one permit can cover both, but depending on your contract the builder may take out their own permit for construction, leaving the owner a 'staged' permit for demolition and landscaping only.

How long does an asset protection permit last?

Boroondara's permit lapses if works don't start within 12 months, then lasts 3 years once they do. Merri-bek's lasts 1 year and can be renewed annually, Monash's lasts 2 years from issue, and Whitehorse's lasts 24 months or while the building permit is valid.

Sources

  1. City of Boroondara: Asset Protection Permit
  2. Darebin City Council: Asset protection
  3. Glen Eira City Council: Asset Protection Permit
  4. Merri-bek City Council: Other construction permits (asset protection)
  5. Merri-bek City Council: Welcome to Merri-bek, City Council name officially changed (26 September 2022)
  6. City of Monash: General Asset Protection Permit
  7. business.gov.au (ABLIS): Asset Protection Permit, City of Monash
  8. Whitehorse City Council: Asset Protection Permits
  9. Whitehorse City Council: Your Property and the Whitehorse Community Local Law
  10. Building and Plumbing Commission (trading name of the VBA): Appointing a building surveyor